Formal bids (those of $100,000.00 or more), are opened by the City Clerk’s office, as they come due, each Wednesday, at 2:00 p.m.
Informal bids (those less than $100,000.00), are opened by each requesting department, as announced in the bid solicitation. It has been suggested that informal bids, and bids let under the Sheltered Market Program, be opened on Monday, Tuesday, or Friday, at either 10:00 a.m. or 2:00 p.m. (See Bidding Process for more information.)
Purchasing and other City departments' informal bids are opened at the time and day of the week specified in the announcement.
Please allow the Project Manager about two weeks to conduct the bid analysis before making contact regarding final bid result.
| Project |
Project Manager |
Date Opened |
Bid Responses |
Bid Amount |
Cable & Strength Fitness Equipment
(B082157021)
(....Bids Received) |
John Hanson |
12-28-2007 |
Canceled |
|
Cardio Fitness Equipment
(B082157022)
(....Bids Received) |
John Hanson |
12-28-2007 |
Canceled |
|
Unarmed Security Guard Services
(B081181035)
(5 Bids Received) |
Sonny Eboigbe |
12-27-2007 |
Comprehensive Securty
Universal Protection
National Security
American Corporate security
International Svcs. Inc |
$1,886,990.56
$1,975,967.24
$2,052,296.00
$2,087,946.60
$2,130,987.82
|
Convention Center Compex Dance Floor
(B084326003)
(3 Bids Received) |
Melanie Medina |
12-21-2007 |
Sico America, Inc.
The Master Floor Co.
Mity-Lite, Inc. |
$43,050.00
$43,541.00
$54,226.76
See Bid Eval |
West Natomas Central (B083497007)
(8 Bids Received) |
Stephanie Fraser |
12-20-2007 |
Rousch Landscape
Valley Landscape
Empire Landscape
Oliver Landscape
Cazares Landscape |
$10,006.00
$16,430.00
$17,250.00
$18,625.00
$23,100.00
See Bid Eval |
Willow Creek (B083497009)
(9 Bids Received) |
Stephanie Fraser |
12-20-2007 |
Dominguez Landscape
Empire Landscape
Cazares Landscape
California Landscape
Oliver Landscape |
$28,800.00
$29,400.00
$32,400.00
$40,932.00
$41,400.00
See Bid Eval |
South East Commerce (B083497006)
(8 Bids Received) |
Stephanie Fraser |
12-20-2007 |
Empire Landscape
Cazares Landscape
Valley Landscape
Plantech Landscape
California Landscape |
$20,450.00
$21,300.00
$21,230.0
$30,510.00
$30,558.00
See Bid Eval |
Palm Gateway (B083497008)
(9 Bids Received) |
Stephanie Fraser |
12-20-2007 |
Empire Landscape
Cazares Landscape
Oliver Landscape
Plantech Landscape
California Landscape |
$26,250.00
$33,300.00
$29,400.00
$34,350.00
$35,974.00
See Bid Eval |
North East Commerce (B083497005)
(8 Bids Received) |
Stephanie Fraser |
12-20-2007 |
Plantech Landscape
Valley Landscape
Empire Landscape
Dominguez Landscape
Cazares Landscape |
$28,350.00
$29,690.00
$34,450.00
$37,200.00
$39,300.00
See Bid Eval |
Animal Care (B083497004)
(7 Bids Received) |
Stephanie Fraser |
12-20-2007 |
Roush Landscape
Empire Landscape
California Landscape
Cazares Landscape
Oliver Landscape |
$9,574.00
$9,930.00
$11,382.00
$11,700.00
$12,025.00
See Bid Eval |
Sump 131 Pump Station Electrical Improvements (B083331013)
(7 Bids Received) |
JianZhuang |
12-19-2007 |
JR Shap Construction
Velici Construction
AMI Electric
Dornbier Electric
BRC Construction Inc |
$69,332.00
$72,900.00
$79,000.00
$83,460.00
$85,500.00 |
North Laguna Walking Trail - Phase 2 (B084727017)
(11Bids Received) |
Jeff Nittka |
12-18-2007 |
Southwest Grading, Inc
David Engineering Const
Macauley Construction
Daniel Velici
Shane Thomas |
$21,848.00
$22,586.00
$22,929.00
$23,850.00
$23,947.00
See Bid Eval
. |
Repair and Overhaul of G398 Caterpillar Engine at Florin Reservoir (B083351009)
(3 Bids Received) |
Royce Bedrosian |
12-17-2007 |
Rancho Cordova Independent Diesel
Holt of California
Peterson Power |
$68,886.80
$97,923.00
$123,142.00 |
| R Street Market Plaza Project 16th Street to 18th Street (P083431005) |
Cecilyn Foote |
12-07-2007 |
Not Yet Available |
|
Department of Utilities Financial Audit and Review (P083351007) (0 Proposals Received) |
Karen Lane |
12-05-2007 |
Canceled |
|
Armored Car Services (B081181038)
(2 Bids Received) |
Marc Robles |
12-05-2007 |
Loomis Armored
AT-Systems |
$129,788.00
$318,809.48 |
American River Watershed Sanitary Survey 2008 Update (P083351006)
(3 Proposals Received) |
Elissa Callman |
12-05-2007 |
Starr Consulting
Forsgren
PBS&J |
$102,020.00
$124,112
$139,959 |
On Call Material Sampling & Geotechnical Testing Services (Q083275013)
(19 Qualifications Received) |
Katherine Robbins |
11-29-2007 |
Youngdahl
Construction Testing Services
Wallace & Kuhl
Matriscope
Inspection Consultants |
|
Chain and Flight SRWTP Grit Basin (B083350053)
(1 Bid Received) |
Michelle Carrey |
11-28-2007 |
Siemens Water Technology |
$34,295.00 |
Type 1 Ambulances (B081181034)
(5 Bids Received) |
Christine Slay |
11-26-2007 |
Golden West Trailers
Emergency Vehicle Grp
Taylor Made Ambulances
Wheeled Coach
Road Rescue |
$1,228,184.09
$1,296,090.18
$1,297,951.06
$1,352,662.20
$1,429,161.60
See Bid Eval |
Command Vu Vi Display Screen (B081181040)
(1 Bid Received) |
Christine Slay |
11-26-2007 |
L3 Communications |
$194,938.50 |
Gobooks (B081181039)
(1 Bid Received) |
Christine Slay |
11-26-2007 |
Raymar Information Tech |
$211,250.73 |
Chuck Wagon Park (LY89)
(B084727015)
(10 Bids Received) |
Julia Cox |
11-21-2007 |
SGC Construction
David Eng. Construction
Vellici Construction
Parker Landscape Dev.
K&L General Engineers |
$76,386.00
$78,615.00
$86,000.00
$87,015.70
$89,603.00
See Bid Eval |
Oak Park Street Lighting (B083431010)
(10 Bids Received) |
Kaleb Haile |
11-21-2007 |
Norwood Construction
Royal Electric
Hudson Excavation
Moreno Trenching Ltd.
Pacific Excavation |
$778,250.00
$833,780.00
$835,510.20
$889,273.41
$1,017,762.00 |
East Sacramento Water Meter Retrofit (B083331011)
15 Bids Received) |
Chris Powell |
11-21-2007 |
Teichert Construction
Preston Pipelines
Navajo Pipelines
Vulcan Construction
Florez Paving |
$1,269,140.00
$1,269,904.00
$1,365,600.00
$1,411,200.00
$1,429,750.00 |
Pelican LED Flashlights (B081181036)
(23 Bids Received) |
Christine Slay |
11-21-2007 |
LC Action
Roguetactical
L.N. Curtis & Sons
Airgas
Empire Safety |
$103,345.32
$107,889.08
$107,856.40
$107,889.08
$108,878.66
See Bid Eval |
Sacramento Public Library Public Relationship Project (SPL1082007)
(5 Proposals Received) |
Gary Shaffer |
11-19-2007 |
Astone Crocker Flanagan
Landor
Siegel+Gale
Springboard
Two West
|
|
Labor Compliance Field Investigation and Administrative Services (P083112012)
(5 Proposals Received) |
Malyssa Berry |
11-16-2007 |
Diversified Contract Management Group
WCS CA
Parsons Brinckerhoff
Kurey & Associates Affordable Designs |
|
Westlake Park Phase 2 (LS78)
(B084727014)
(11 Bids Received) |
Roy Tatman |
11-14-2007 |
PBM Construction
Parker Landscape
Gold Valley Construction
Hemington Landscape
AdLand Venture |
$779,779.00
$800,459.00
$821,198.08
$822,630.00
$822,731.99
See Bid Eval |
O.E.M. Parts for Trucks & Equipment (B081181030)
(5 Bids Received) |
Marc Robles |
11-14-2007 |
Bobcast West
Arborquip Corp.
United Rotary Brush
Pape' Machinery Inc.
MME |
|
O.E.M. Parts for Heavy Equipment (B081181031)
(2 Bids Received) |
Marc Robles |
11-14-2007 |
Holt of California
H.V. Carter Co. Inc. |
$150,000.00
$200,000.00 |
Radio Activated GPS-Based Traffic Signal Priority Control System (B081181037)
(1 Bid Received) |
Angie Louie |
11-14-2007 |
Advanced Traffic |
$365,394.27
See Bid Eval |
Memorial Auditorium Exterior Cleaning (B083275010)
(6 Bids Received) |
Mike George |
11-07-2007 |
Velici Construction
Rainbow Waterproofing
Giampolini & Co.
Forrest Stone
Fix Painting Co. |
$94,000.00
$132,624.00
$142,937.00
$149,000.00
$172,000.00 |
Street Light Parts - Ballasts (B081181025)
(7 Bids Received) |
Craig Lymus |
10-31-2007 |
Comtrex
Granite Electric Supply
Wesco
Graybar
General Electric |
$31,678.70
$170,458.73
$172,684.19
$175,728.45
$205,408.67 |
Street Light Parts - Lamps (B081181024)
(7 Bids Received) |
Craig Lymus |
10-31-2007 |
Tanko Streetlighting
Graybar
Granite Electric Supply
Sesco Data Systems
Wesco |
$205,681.28
$220,165.57
$239,285.82
$268,887.43
$270,612.78 |
Street Light Parts - Fixtures (B081181023)
(5 Bids Received) |
Craig Lymus |
10-31-2007 |
Wesco
Granite Electric Supply
Hi-Line Electric
Graybar
General Electric |
$112,016.90
$115,028.78
$115,049.36
$115,651.84
$131,155.45 |
FWTP Low Lift Pumps - Phase II (B083331010)
(7 Bids Received) |
Jian Zhuang |
10-31-2007 |
Central Pacific Const.
MIB Enterprises
Johnson Mechanical Co.
JR Sharp Construction
BRC Construction |
$168,000.00
$186,000.00
$280,000.00
$302,868.00
$327,369.00 |
2007 City Bridge Repair Project-Phase 1 (RA26) (B083431009)
(8 Bids Received) |
Ricky Chuck |
10-31-2007 |
Debruin Construction
Contractors Chemical Inc.
Viking Construction
ACC West Coast, Inc.
RNR Construction |
$94,880.50
$114,815.20
$147,598.00
$153,072.00
$164,259.00
See Bid Eval |
Street Light Parts - Poles (B081181027)
(5 Bids Received) |
Craig Lymus |
10-31-2007 |
General Electric
Granite Elect Supply
Wesco
Hi-Line Electric
Graybar |
$71,299.25
$194,031.09
$210,798.06
$214,060.89
$224,240.30 |
Street Light Parts - Lenses (B081181026)
(5 Bids Received) |
Craig Lymus |
10-31-2007 |
Granite Elect. Supply
Hi-Line Electric
Wesco
Graybar
General Electric |
$106,967.74
$176,104.18
$221,601.34
$273,766.35
$330,038.25 |
Waste-to-Energy RFQ (Q080310001)
(11Qualifications Received) |
Michelle Heppner |
10-26-2007 |
ERN
Internation Environmental Solutions
Firm Green Energy, inc
The Zanker Group
ReCycled Refuse Internaitonal AG
Aerojet |
|
Roseville Road Bridge Replacement RFP
(P083431004)
(7 Proposals Received) |
Matthew Johns |
10-26-2007 |
David Evans and Assoc
Lim & Nascimento
Mark Thomas & Co
Quincy Engineering, Inc
TRC
URS
Wood Rodgers
|
|
Request for Qualification - Security Services (Q081181032)
(12 Qualifications Received)
|
Sonny Egoigbe |
10-26-2007 |
American Corp
Comprehensive Security
DWB Protective
International Services
Monument Security
|
|
North Laguna Creek Recreation Trail (LW91) (B084727013)
(9 Bids Received) |
Jeff Nittka |
10-24-2007 |
All Phase Construction
Biondi Paving
K & L General Engineering
Central Valley
Ram's Construction & Landscaping |
$30,254.65
$32,380.00
$33,581.00
$34,087.00
$36,267.60
See Bid Eval |
RFQ On Call Material Sampling & Geotechnical Testing Services (B083275009)
(... Qualifications Received) |
Yadi Kavakebi |
10-24-2007 |
Not Yet Available |
|
Intergrated Pest Managment Services (B081181018)
(8 Bids Received) |
Marc Robles |
10-24-2007 |
Ecolab
True Value Pest Control
Applied Pest Management
Advanced Integrated Pest
Hunters Pest Control |
$29,472.00
$38,460.00
$42,024.00
$42,288.00
$64,980.00 |
North Natomas Bike Trail (B083497003)
(6 Bids Received) |
Stephanie Fraser |
10-22-2007 |
Cazares Landscape
Coast Landscape
Oliver Landscape
Valley Landscape
Empire Landscape |
$10,800.00
$11,378.00
$12,600.00
$15,120.00
$16,680.00 |
Soundwalls and Pedestrian Bridges (B083497002)
(7 Bids Received) |
Stephanie Fraser |
10-22-2007 |
Plantech Landscape
Roush Landscape
Empire Landscape
Venegas Landscape
Oliver Landscape
|
$32,560.00
$33,836.00
$35,320.00
$38,360.00
$41,700.00 |
Counseling Services for Attendance Centers (P082142001)
(13 Proposals Received) |
Lt. Neil Schneider |
10-19-2007 |
Another Choice Another
La Familia Counseling Cnt
EMQ Children and Family
Southeast Asian Vision
The Dream Collective |
|
Titan Assault Vests (B082123020)
(4 Bids Received) |
Lt. Steve Campas |
10-19-2007 |
L.C. Action
Adamson Police
Blumenthal Uniforms
Command Uniforms |
$34,078.95
$34.867.90
$36,591.90
$36,887.25 |
Study to Develop a Program to "Light the City"
(P084915002)
(... Proposals Received) |
Bob Cooper |
10-17-2007 |
Canceled |
|
Preparation of City Annual Cost Allocation Plan
(P081140001)
(3 Proposals Received) |
Scott Pettingell |
10-17-2007 |
MGT |
|
Parking Citation Printing Services (B081181014)
(2 Bids Received) |
Rochelle Freyman |
10-17-2007 |
Regal Forms, Inc.
New Direction Services |
$16,400.00
$158,000.00 |
Generator Sets (B081181016)
(3 Bids Received) |
Paul Barnes |
10-17-2007 |
Nevada Energy Sys, Inc.
Holt of California
Collicutt Energy Svcs, Inc. |
$1,054,389.07
$1,383,855.00
$1,551,750.25
See Bid Eval |
Cargo and Passenger Minivans (B081181021)
(0 Bids Received) |
Marc Robles |
10-17-2007 |
Canceled |
|
13th St Water Transmission Main Replacement Project H to Q Street (P083351005)
(7 Proposals Received) |
Michelle Carrey |
10-17-2007 |
Shannon and Wilson, Inc
Stevens, Ferrone & Bailey Engineering Co,
Sander & Associates
Krazan & Associates
Taber Consultants
Fugro West, Inc
Terrasearch, Inc |
|
| La Mancha Way Bridge over Elder Creek Rehabilitation (9431) (B083431008)
(7 Bids Received) |
Ricky Chuck |
10-16-2007 |
G. Bianchi Construction
Altman General
RNR Construction
R.A. Memetz Const.
Martin Brothers Const. |
$57,999.12
$58,620.00
$59,550.00
$62,550.00
$69,715.00
See Bid Eval |
Janitorial Supplies (B081181017)
(16 Bids Received) |
Craig Lymus |
10-12-2007 |
NDJ Enterprises
UniPak Corp
Interboro Packaging Corp.
Central Poly Corp
All American Poly |
$6,239.80
$17,875.00
$28,679.00
$36,197.50
$42,279.50
See Bid Eval |
Fibar Fall Material (B084728003)
(2 Bids Received) |
Barbara Collins |
10-12-2007 |
La Forme Trucking
M.F. Filice & Son Surfaces |
$17,906.00
$24,486.88
See Bid Eval |
Field Renovation Sand (B084728006)
(2 Bids Received) |
Barbara Collins |
10-12-2007 |
Beebe Industries, Inc.
Silica Resources, Inc. |
$43,872.50
$44,024.88
See Bid Eval |
Field Renovation Material (B084728005)
(3 Bids Received) |
Barbara Collins |
10-12-2007 |
Sierra Pacific Turf Supply
Western Exterminator Co.
Linwood Supply, Inc. |
$23,433.74
$23,551.46
$38,401.02
See Bid Eval |
Fibar Fall Material Delivery/Blowing (B084728004)
(1 Bid Received) |
Barbara Collins |
10-12-2007 |
M.F. Filice & Son Surfaces |
$21,100.63
See Bid Eval |
Access Improvements - Railyards to Richards Blvd & Interstate 5 (P083431003)
(4 Proposals Received) |
Ted Davini |
10-12-2007 |
David Evan & Associates
Carter Burgess
GC Wallace
Mark Thomas & Company |
|
Ninos Pkwy Phase 1B and 1C REBID (HC61) (B083431007)
(10 Bids Received) |
Ricky Chuck |
10-10-2007 |
Biundo Landscape Const.
Martin Brothers Const.
Granite Construction Co.
Gold Valley Const.
K & L General Eng. |
$347,504.00
$352,259.00
$355,986.50
$363,208.50
$365,739.20
See Bid Eval |
Fulton Ave Extension Project (CB37) (B083431006)
(16 Bids Received) |
Jon Blank |
10-10-2007 |
Marques Pipeline
Independent Construction
DeSilva Gates
C & D Contractors
Teichert Construction |
$2,255,979.00
$2,256,701.57
$2,257,418.40
$2,274,158.00
$2,299,568.30
See Bid Eval |
|
|
|
|
|
Medium Duty Trucks (B081181011)
(4 Bids Received) |
Marc Robles |
10-10-2007 |
Riverview Int'l Truck
Sacramento Truck Center
Downtown Ford Sales
Bonander Truck |
$1,213,980.34
$1,300,000.00
$2,178,656,25
$2,466,753.31 |
Consulting Services for Analysis of Fire Department Schedule Change (P081541001)
(4 Proposals Received) |
Barbara Brenner |
10-08-2007 |
Bickmore Risk Services
Aon Risk Services
Matix Consulting Group
McCabe Consultants |
|
RFQ for Information Technology Consulting Service (Q081311001)
(... Qualifications Received) |
Ignacio Estevez |
10-04-2007 |
Canceled |
|
Steve Jones Park Detention Basin Project (WJ96) (B083331001)
(18 Bids Received) |
StuWilliams |
10-03-2007 |
Emard Engineering
Central Pacific Const.
Westcon Construction
Yubacon Inc.
AC General Engineering |
$166,600.00
$198,779.00
$198,814.00
$225,376.00
$227,966.00 |
Del Paso Park Shade Structure (LY11) (B084727012)
(3 Bids Received) |
RoyTatman
|
10-03-2007 |
Comm. Playground Inc.
Bonateck Engineering
SGC Construction |
$33,280.00
$60,000.00
$72,139.00 |
Fire Advanced Life Support (ALS) Lockbox Services (B081181001)
(1 Bid Received) |
Sonny Eboigbe |
10-03-2007 |
U.S. Bank |
$17,489.50 |
Uniform Rental and Cleaning Service (B081181019)
(2 Bids Received) |
Rachel Rosas |
10-03-2007 |
Mission Linen & Uniform
Unifirst |
$261,069.80
$263,688.61
See Bid Eval |
Truck with Utility Bed and Crane (B083259019)
(3 Bids Received) |
Bill Tierce |
10-01-2007 |
E.R. Bacon Co.
Downtown Ford
Bonander Truck |
$88,350.00
$90,402.25
$95,710.02 |
Convention Center Complex Boiler Meter Purchase, Installation, and Maintenance Contract (B084326002)
(2 Bids Received) |
Tina McCarty |
09-28-2007 |
Emcor Service
Indoor Enviromental Svcs |
$41,994.00
$52,490.00
See Bid Eval |
Hagginwood & Johnston Parks Shade Structures (LM58) (B084727010)
(9 Bids Received) |
SueAkiyama |
09-26-2007 |
SGC Construction
Bonatech Engineering
Buildream Inc.
Community Playgrounds
U.S.A. Shade & Fabric Structures |
$85,366.00
$90,000.00
$98,485.00
$103,736.00
$105,689.87
See Bid Eval |
Fresh Fruits and Vegetables (B081181012)
(1 Bid Received) |
Christine Slay |
09-26-2007 |
JC Produce |
$203,247.00 |
McAfee Total Protection Enterprise Maintenance License (B081313003)
(17 Bids Received) |
Rick Hellewell |
09-25-2007 |
Cyber Computers
CCT Technologies
Dell Marketing
CDW-G
Zones Inc. |
$43,341.00
$45,499.25
$45,697.05
$45,908.50
$46176.45
See Bid Eval |
Max Baer Tot Lot
(B084727011)
(....Bids Received) |
Julia Cox |
09/20/07 |
Not Yet Available |
|
Teaching Artists in Dance, Theatre & Visual Arts (P084241002)
(... Proposals Received) |
Erika Kraft |
09-19-2007 |
Canceled |
|
Original Equipment Manufacturer (O.E.M.) Parts and Services for Refuse Trucks (B081181015)
(3 Bids Received) |
Marc Robles |
09-19-2007 |
Ray Gaskin Svc
Nick Arata
Pleasanton Truck & Equip. |
$84.00 hr.
$100.00 hr.
$100.00 hr. |
FWTP Clarifier Motor Control Center (MCC) Replacement (ZL56) (B083331009)
(4 Bids Received) |
JianZhuang
|
09-19-2007 |
BRC Construction
JR Sharp Construction
Interstate Construction
Central Pacific Const. |
$98,647.00
$99,950.00
$174,676.00
$178,000.00 |
Investment Banking/Financial Advisor Services (P080900001)
(5 Proposals Received) |
Janelle Gray |
09-17-2007 |
Stone & Youngberg
Goldman Sachs
Merrill Lynch Pierce Fenner & Smith Inc
Sutter Securities
Siebert Brandford Shank & Co
|
|
South East Sacramento Bike & Pedestrian Access Study RFP (P083431001)
(3 Proposals Received) |
Mathew Jones |
09-14-2007 |
Fehr & Peers Transportation
Alta Planning & Design
WRG Design, Inc. |
|
Weed Abatement and Debris Removal SVCS (B081181013)
(6 Bids Received) |
Rachel Rosas |
09-13-2007 |
Ram's Const
TruGreen
NCRM
All You Need Lawn
Baylor Services |
$6,288.00
$9,035.00
$38,782.00
$33,560.00
$38,782.00
See Bid Eval |
SurfControl Web/Email Filter Maintenance Contract 1yr (B081313002)
(4 Bids Received) |
Rick Hellewell |
09-13-2007 |
Accuvnat
CDW-G
Right Systems Inc.
Adeara |
$46,225.00
$48,931.00
$52,713.00
$56,525.00
See Bid Eval |
Sacramento Intermodal Transit Facility & Track Relocation (P083431002)
(... Proposals Received) |
Saed Hasan |
09-13-2007 |
Not Yet Available |
|
Booster Pump & Central Irrigation Installation (LW82)
(B081181008)
(3 Bids Received) |
Jim Bacchini |
09-12-2007 |
Ad Land Venture
Olympic Land Const.
Gold Valley Const. |
$367,725.00
$399,800.00
$550,095.01 |
Nuevo Park Improvements (LM96) (B084727008)
(7 Bids Received) |
Dennis Day |
09-12-2007 |
Solo Landscaping
Central Pacific Const.
K & L General Engineering
Olympic Land Const.
Biundo Landscape Const. |
$231,622.45
$246,000.00
$247,165.35
$251,958.00
$253,850.00
See Bid Eval |
Brookfiedl/Mack Landscaping Project (LQ01) (B084727009)
(6 Bids Received) |
Julia Cox |
09-12-2007 |
Empire Landscaping
JM Slover Inc.
Parker Landscape Dev.
TRU Green Landcare
Pittman Engineering |
$126,000.00
$127,865.00
$149,519.00
$150,782.00
$151,200.00
See Bid Eval |
Liquified Natural Gas (LNG) Delivery Truck (B081181010)
(3 Bids Received) |
Marc Robles |
09-12-2007 |
Riverview Int'l Trucks
Sacramento Truck Center
Bonander Truck |
$437,390.00
$441,445.81
$489,152.94 |
2007 On-Call Transportation Specialty Services RFQ
(Q083431001)
(245 Qualifications from 80 Consultants Received) |
David Flores, Jr. |
09-11-2007 |
245 Qualifications from 80 Consultants Received |
|
Sump 2 Electrical Improvements Phase 1 XN46(B083331008)
(5 Bids Received) |
Renee Graves |
09-05-2007 |
Clyde G. Steagall Inc
JR Sharp Construction
BRC Construction
Auburn Constructors
Clayborn Contracting Grp |
$1,047,077.00
$1,092,000.00
$1,198,375.00
$1,199,300.00
$1,289,371.00 |
Cabrillo Park-Tennis Court
Renovation LL97
(B084727007)
(3 Bids Received) |
Tim Hopper |
09-05-2007 |
Biondi Paving
Sierra Asphalt
Martin Brothers Const |
$48,800.00
$54,350.00
$68,297.00 |
North Laguna Bike Trail Rehabilitation (HC47)
(B084727005)
(10 Bids Received) |
JeffNittka |
08-29-2007 |
K & L General Engineering
AC General Engineering
Central Valley Engineering
Western Engin. Contr.
Sierra Asphalt |
$263,184.00
$276,440.00
$281,043.60
$289,279.25
$290,829.00 |
Shade Structures at Various Playgrounds: North Pointe & Robertson Parks (LM58) (B084727006)
(5 Bids Received) |
SueAkiyama |
08-29-2007 |
SGC Construction
Solo Landscaping
Olympic Land Const.
Bonatech Engineering
LG General Contractors |
$79,821.00
$87,200.00
$89,364.00
$93,000.00
$115,562.00
See Bid Eval |
Sacramento River Water Treatment Plant (SRWTP) 9.5 MG Reservoir Roof Replacement (ZH51) (B083331004)
(6 Bids Received) |
WarrenPeterson
|
08-29-2007 |
Madsen Roof Co.
Advantage Bldg Contr.
C & C Construction
Younger General Contr.
Best Inc. |
$1,067,983.00
$1,314,000.00
$1,459,000.00
$1,586,000.00
$1,941,300.00 |
Mack Road Streetscapes
(B083497001)
(4 Bids Received) |
Stephanie Fraser |
08-29-2007 |
Dominguez Landscape
Casares Landscape
Ram Construction
East Bay Construction |
$37,560
$40,800
$45,480.61
$158,153.04 |
On-Call Cabinet & Countertop Services (B083275007)
(2 Bids Received) |
Mike Trapp |
08-24-2007 |
Holm's Wood Works
Gold Country Cabinets |
$85.00 per hr.
$105.00 per hr. |
On-Call Drywall Services (B083275006)
(2 Bids Received) |
Bill Conner |
08-24-2007 |
Ram Construction
C.M. Long |
$60.00 per hr.
$85.00 per hr. |
On-Call Stucco Services (B083275003)
(2 Bids Received) |
Bill Conner |
08-24-2007 |
C.M. Long
SAC Plaster & Design |
$85.00 per hr.
$111.00 per hr. |
On-Call Irrigation Services
(B083275001)
(5 Bids Received) |
Louie Maldonado |
08-24-2007 |
Dominguez Landscape .
Rams Const. & Landscape
CA Landscape Assoc.
TruGreen Landscape
Paul Velasquez |
$47.50 per hr.
$50.00 per hr.
$52.00 per hr.
$65.00 per hr.
$94.50 per hr. |
On-Call Plumbing Services
(B083275004)
(2 Bids Received) |
Louie Maldonado |
08-24-2007 |
Luppen & Hawley
Paul Velasquez Eng. |
$100.00 per hr.
$100.00 per hr. |
On-Call Pumping Services
(B083275005)
(2 Bids Received) |
Louie Maldonado |
08-24-2007 |
Custom Pump & Power
Kirby's Pump & Mech. |
$90.00 per hr.
$97.00 per hr. |
On-Call Trenchless Services (B083275002)
(3 Bids Received) |
Louie Maldonado |
08-24-2007 |
Shasta General Eng.
Greenberg Clark
Express Plumbing |
$42.00 per ft.
$65.00 per ft.
$69.00 per ft. |
Drinking Water Residuals Sludge Trucking Services (B083351004)
(4 Bids Received) |
Craig Chalmers |
08-24-2007 |
Dillard
Empire Trucking
Chavez
Manley |
$94,145.00
$94,224.00
$94,250.00
$94,250.00 |
California Air Resources Board Diesel Particulate Filters Including Installation
(B081181007)
(4 Bids Received) |
Marc Robles |
08-22-2007 |
Riverview International
A-Z Bus Sales
Cummins West
Iron Man Parts & Services |
$327,480.00
$683,692.30
$1,110,934.00
$1,192,356.60 |
Window Washing Services (B081181005)
(6 Bids Received) |
Marc Robles |
08-22-2007 |
20/20
RCM Window Cleaning
Pacific Maintenance Co.
High Rise Windows
Anago of Sacramento |
$55,059.00
$62,690.00
$67,833.00
$83,060.00
$144,890.00
|
Verano Creek Park (LT72)
(B084727003)
(6 Bids Received) |
Jeff Nittka |
08-22-2007 |
Parker Landscape Dev.
JM Slover Inc.
K & L General Engineering
Olympic Land Construction
Gold Valley Construction |
$306,717.00
$314,464.40
$327,905.00
$340,861.00
$345,068.00
See Bid Eval |
Marshall Park Improvements (LX16) (B084727004)
(5 Bids Received) |
Steven Giguere |
08-22-2007 |
Parker Landscape Dev.
Gold Valley Construction
C & C Construction
Olympic Land Construction
Martin Brothers Construction |
$187,448.38
$199,452.25
$212,148.00
$253,316.00
$260,200.00 |
Capitol Garage Painting Project (VD82) (B084727003)
(8 Bids Received) |
Lori Fox |
08-22-2007 |
El Greco Construction
Horizon Painting
Bay View Painting
Euro Style Maintenance
Affodable Painting Service |
$193,998.00
$243,200.00
$254,000.00
$261,500.00
$296,290.00 |
Printing Services (Q083351003)
(5 Qualifications Received) |
Jessica Hess |
08-20-2007 |
Brownie's
Signature Reprographics
Graphic Focus
Action Printers
Zuprinco Printing |
|
Miscellaneous Sewer Service Lining 2008 (XI96)
(B083331007)
(3 Bids Received) |
Melissa Rollins |
08-17-2007 |
The Trenchless Co.
Mr. Rooter Plumbing
Pacific Liners |
$83,520.00
$88,000.00
$142,550.00 |
Traffic Signal LED displays (B083498001)
(3 Bids Received) |
Steve Krecek |
08-15-2007 |
Advanced Traffic Products
Hi-Line Electric
Jam Services |
$47,474.00
$49,451.00
$51,891.50
See Bid Eval |
Teaching Artists in Dance, Theatre and Visual Arts (P084241001)
(... Proposals Received) |
Erika Kraft |
08-15-2007 |
Canceled |
|
Official City Newspaper for Advertising (B081181009)
(1 Bid Received) |
Rachel Rosas |
08-15-2007 |
The Daily Recorder |
$9 per inch |
Creative Development, Media Placement and Media Relations (Q083351002)
(5 Qualifications Received) |
Jessica Hess |
08-15-2007 |
Wallrich Landi
KATZ & Associates
IN Communications
TRG & Associates
LUCY & Company |
|
J Street Sewer Replacement 18th to 20th Street (XN51) (B083331005)
(4 Bids Received) |
RosaMillino
|
08-15-2007 |
AC General Engineering
Florez Paving
Frank Medina GEC
Navajo Pipelines |
$156,598.00
$203,632.00
$207,870.00
$266,807.00
See Bid Eval |
S-T Street Alley, 18th to 19th Street Sewer Replacement (XN55) (B083331006)
(3 Bids Received) |
MarkElliott
|
08-10-2007 |
Florez Paving
Navajo Pipelines
AC General |
$77,950.30
$84,675.00
$89,365.00 |
Three-Way Perennial Ryegrass (B084280001)
(5 Bids Received) |
Mike Kerton |
08-09-2007 |
Wilbur-Ellis
Western Exterminator
Dixon Hardware
Sierra Pacific Turf Supply
Western Farm Service |
$31,680.00
$32,040.00
$33,480.00
$33,480.00
$33,840.00
See Bid Eval |
Parking Enforcement Scooters (B081181006)
(1 Bid Received) |
Marc Robles |
08-08-2007 |
Municipal Maint. Equipment |
$655,284.26 |
O.E.M. Parts and Services for Various Manufacturers (B071181099)(7 Bids Received) |
Marc Robles |
08-08-2007 |
Harold Ford
Dowtown Ford Sales
Ozzies BMW Center
Senator Ford Inc
Ron Dupratt Ford |
$65 hr mech
$70 hr mech
$72 hr mech
$75 hr mech
$79 hr mech |
Capitol/L Alley Sewer Replacement 18th-19th St XN38(B083331002)
(6 Bids Received) |
Dale Mathison |
08-08-2007 |
AC General Engineering
Navajo Pipelines Inc
Florez Paving
MIB Enterprises
Toni Medina |
103,887.00
109,085.00
119,810.40
125,940.00
136,444.00 |
William Land Park Jogging Path LW72(B084727002)
(10 Bids Received) |
Roy Tatman |
08-08-2007 |
American Landscape
Solo Landscaping
Sunworld
Pittman Engineering
BP Landscapes Inc |
154,634.00
155,600.00
180,740.00
194,019.00
211,500.00
See Bid Eval |
Medical Screenings/Physicals (B081181008A)
(1 Bids Received) |
Shawn Perry |
08-08-2007 |
Mercy Medical Group,
Occupational Health Services
|
|
34th/35th Street Alley Combined Sewer Replacement - Folsom Blvd. to P Street (XN39)
(B083331003)
(8 Bids Received) |
DaleMathison |
08-08-2007 |
Florez Paving
Navajo Pipelines
AC General Engineer
MIB Enterprises
Toni Medina |
$168,913.00
$170,702.00
$185,000.00
$202,658.00
$226,375.00
See Bid Eval |
Landscape Maintenance Service for the Meadowview City Service Complex (B081181002)
(11 Bids Received) |
Rochelle Freyman |
08-03-2007 |
Thompson Landscaping
Moodey Inc.
Empire Landscaping
JFD Enterprises
Cazares Landscape and Maint. |
$9,204.00
$26,400.00
$28,800.00
$38,160.00
$38,400.00 |
Remington Brand Shotguns (B082124019)
(4 Bids Received) |
Milt Payne |
08-02-2007 |
LC Action Police Supply
All State Police Equip.
Proforce Law Enforce.
River City Gun Exchange |
$35,378.25
$35,925.00
$36,169.50
$36,787.50
See Bid Eval |
Conlin Youth Sports Complex-Phase 3 (KB34) (B084727001)
(6 Bids Received) |
Julia Cox |
08-01-2007 |
Western Engineering
C & C Construction
Westcon Construction Corp.
Olympic Land Const.
Biondi Paving |
$519,854.65
$556,807.00
$570,408.82
$572,894.85
$602,315.50
See Bid Eval |
Towing and Storage Services (B081181003)
(3 Bids Received) |
Christine Slay |
08-01-2007 |
Cheaper Towing Inc.
Capital City AutomotiveCapital A1Towing |
$52,958.00
$67,425.00
$85,965.00 |
Convention Center Complex Landscape Contract (B084326001)
(8 Bids Received) |
Tina McCarty |
07-31-2007 |
Moodey Inc
Empire Landscaping
Cazares
JFD Enterprises
California Landscape
Pacific Maint |
$18,720
$19,800
$21,600
$22,380
$22,452
$40,008 |
Urban Search & Rescue Back Packs (B081181004)
(1 Bid Received) |
Vatsala Gaylor |
07-27-2007 |
Canceled-Non Responsive |
|
Hart Senior Center Exterior Lighting Improvements (B073282040)
(6 Bids Received) |
JamesChristensen
|
07-27-2007 |
Collins Electrical Co.
Royal Electric
Nation One Electric
Glodus Electric
Alpha Electric |
$60,469.00
$62,505.00
$88,630.72
$88,838.00
$94,300.00
See Bid Eval |
Pest Control Services for Ponds - REBID (B084728001)
(... Bids Received) |
Barbara Collins |
07-27-2007 |
All Bids Have Been Rejected |
|
Pest Control Services - REBID
(B084728002)
(7 Bids Received) |
Barbara Collins |
07-27-2007 |
Hunters Pest Control
JFD Enterprises
Landscape Weed & Pest
Pegasus Pest Control
California Majestic |
$18,356.50
$19,736.00
$20,335.00
$26,150.00
$36,402.00
See Bid Eval |
Capitol Garage Retail Arcade Signage (P073431010)
(2 Proposals Received) |
Lori Fox |
07-26-2007 |
Weidner Architectural Signage
Flouresco Lighting and Signs |
|
2007 Speed Humps Project (SH89) (B083431004)
(6 Bids Received) |
Saed Hasan |
07-25-2007 |
Florez Paving
Biondi Paving
AC General Engineering
Valley Slurry Seal
Intermountain |
$183,212.00
$222,882.00
$242,974.00
$253,489.00
$306,196.70
See Bid Eval |
Ninos Parkway Phase 1B and 1C (HC61) (B083431003)
(12 Bids Received) |
Ricky Chuck |
07-25-2007 |
Biundo Landscape
Western Engineering
Granite Const.Co.
Martin Bros. Const.
Gold Valley Const. |
$359,996.50
$369,978.00
$385,842.00
$387,259.00
$395,269.00 |
2007 Federal Street Overlay (RM73) (B083431002)
(4 Bids Received) |
Zuhair Amawi |
07-25-2007 |
Martin Bros Const.
Granite Const. Co.
Teichert Const.
DeSilva Gates |
$3,395,097.00
$3,562,562.85
$3,668,623.35
$3,857,957.00
See Bid Eval |
2007 City Street Overlay - Ramona Ave Project (B083431001)
(7 Bids Received) |
Ricky Chuck |
07-25-2007 |
Martin Bros. Const.
Biondi Paving
James Riolo Paving
AC General Engineering
Vintage Paving Co. |
$134,755.00
$141,181.00
$144,990.00
$149,355.00
$152,555.00 |
Cattery Facility - Animal Care Center (B073282039)
(13 Bids Received) |
Dave Morgan |
07-25-2007 |
Advantage Bldg Con
River View Const.
C & C Const. Inc.
Combs Const. Inc.
Total Team Const. |
$740,000.00
$773,487.00
$806,909.00
$821,000.00
$839,000.00
See Bid Eval |
Street Light Poles (B071181094)
(5 Bids Received) |
Christine Slay |
07-25-2007 |
Jam Services
Wesco
Hi-Line Electric Co
Granite Electric Co
Relia Pole Solutions |
$241,921.11
$262,272.03
$299,216.63
$334,698.44
$367,804.63
See Bid Eval |
Valley Hi North Laguna Library RFP (P073282037)
(1 Proposals Received) |
Jeff Blanton |
07-20-2007 |
Sundt Construction |
|
Three Wheeled Street Maintenance Brooms
(B083259017)
(3 Bids Received) |
Bill Tierce |
07-19-2007 |
Holt of California
Hertz Equipment
E.R. Bacon |
$40,676.00
$40,702.78
$41,298.00
See Bid Eval |
340 Communication Hub Cabinet (B073431024)
(1 Bid Received) |
Ryan Billeci |
07-18-2007 |
Meyer Power Products |
$28,522.75 |
Emergency Vehicle Accessories
(B083259018)
(5 Bids Received) |
Jonathon Yee |
07-16-2007 |
Emergency Vehicle Solutions
S&G Enterprises
Lehr Auto Electric
The Lighthouse Inc. |
$8,705.00
$25,725.60
$27,722.00
$34,213.80
See Bid Eval |
Equipment Trailers
(B073259015)
(3 Bids Received) |
Jonathon Yee |
07-16-2007 |
Jacobsen Trailer
Holt of Ca Rentals
Edward R. Bacon |
$6,300.00
$6,650.00
$9,257.54
See Bid Eval |
Install VIB's and FIA's on City Owned Equipment
(B073259016)
(1 Bid Received) |
Matt Winkler |
07-16-2007 |
Nationwide |
|
Procurement, Policies, Procedures and Operations
(P071111003)
(7 Proposals Received) |
Tina Lee-Vogt |
07-13-2007 |
Calyptus Consulting Grp
CGI Technologies
Matrix Consultanting
Third Wave
|
$84,670.00
$99,827.00
$75,000.00
$100,000.00 |
Historic City Hall Elevator Alterations (B073275036)
(2 Bids Received) |
TonyAlexander |
07-11-2007 |
Elevator Technology
Capitol Elevator |
$117,800.00
$135,000.00
See Bid Eval |
Recruitment & Management of Student Interns RFQ
(Q073431002)
(1Qualifications Received) |
David Flores |
07-10-2007 |
Community College Foundaiton |
$278,500.00 |
Recycled Cut Paper (B071181097)
(5 Bids Received) |
Sonny Eboigbe |
07-09-2007 |
JC Paper
Xpedex
Ca Envelope & Printing
JM Enterprises
Paper Distributors |
$93,138.43
$99,282.33
$99,655.94
$101,125.75
$107,485.66
See Bid Eval |
Virgin Cut Paper (B071181098)
(5 Bids Received) |
Karen Wright |
07-09-2007 |
Canceled |
|
State Mandated Cost Claiming (P071181096)
(2 Bids Received) |
Sonny Eboigbe |
07-06-2007 |
Maximus
PRM Group |
$10,600.00
$14,900.00 |
MSA Millennium Brand Gas Masks and Accessories (B072124018)
(5 Bids Received) |
Milt Payne |
07-03-2007 |
Safety Supply, Inc.
Adamson Police Supply
Aramsco, Inc.
Global Protection
Federal Resources |
$25,033.76
$27,640.00
$27,714.70
$27,822.50
$28,118.30
See Bid Eval |
Public Safety Center Automatic Gates Installation (B073275038)
(3 Bids Received) |
Tony Alexander |
06-29-2007 |
Dynaram Construction
K & L Engineering, Inc
Golden Bay Fence & |
$44,416.00
$44,500.00
$91,036.00 |
Fire Station #57 Roof Replacement (B073275034)
(4 Bids Received) |
Mike Trapp |
06-29-2007 |
Gudge Roofing
Kodiak Roofing
Hester Roofing
Legacy Roofing |
$65,536.00
$85,190.00
$92,328.00
$106,845.00 |
Fire Station #18 Roof Replacement (B073275033)
(4 Bids Received) |
Mike Trapp |
06-29-2007 |
Gudgel Roofing
Priority Roofing
Hester Roofing
Legacy Roofing |
$42,700.00
$44,968.00
$48,124.00
$49,989.00 |
Fire Station #13 Roof Replacement (B073275032)
(3 Bids Received) |
Mike Trapp |
06-29-2007 |
Gudgel Roofing, Inc.
Hester Roofing, Inc.
Legacy Roofing & |
$115,282.00
$136,515.00
$149,433.00 |
Preparation and Implementation of Final Remediation Plan for the North Area Corporation Yard RFP
(P073282022)
(... Proposals Received) |
Chein Kao |
06-29-2007 |
Not Yet Available |
|
Tilt Bed Trailer (B073259014)
(3 Bids Received) |
Bill Tierce |
06-27-2007 |
Pape Machinery
Holt of California
ER Bacon Co. Inc. |
$21,100.00
$22,400.00
$23,201.85
See Bid Eval |
Sig Sauer Brand Firearms (B072124016)
(5 Bids Received) |
Milt Payne |
06-27-2007 |
Sigarms, Inc.
Pro Force Marketing
Adamson Police Prod.
L.C. Action
River City Gun Exchange |
$43,608.00
$44,184.00
$50,350.00
$52,051.40
$55,670.00
See Bid Eval |
Remington Brand Shotguns (B072124017)
(... Bids Received) |
Milt Payne |
06-27-2007 |
Bid Cancelled - to be Re-bid |
|
Helicopter Maintenance (B071181095)
(1 Bid Received) |
Chris Slay |
06-27-2007 |
San Joaquin Helicopter |
|
Basin 26 Detention at Leonardo Da Vinci School (WI71) (B073331041)
(7 Bids Received) |
Mark Elliot |
06-27-2007 |
Sierra National Construction
Westcon Construction
Emard Electric
McGuire & Hester
Granite Construction Co |
$2,260,720.00
$2,377,498.00
$2,373,000.00
$2,527,113.00
$2,728,127.00
|
Del Paso Road Widening (TW86) (B073431023)
(9 Bids Received) |
Greg Smith |
06-27-2007 |
Sierra Nevada Construction
De Silva Gates
McGuire & Hester
Teichert Construction
Western Engineering |
$3,866,882.85
$3,753,924.00
$3,866,882.85
$3,984,511.65
$3,987,964.68 |
Granite Regional Park Area 2 Lights (B074727022)
(1 Bid Received) |
Roy Tatman |
06-26-2007 |
GrayBar Electirc |
$17,755.21 |
Laboratory Services for Groundwater Analysis (P083351001)
(5 Proposals Received) |
John Olesen |
06-22-2007 |
Calscience Environ. Lab., Inc.
Excelchem Environ. Lab.
SRCSD Water Quality Cont. Lab
TestAmerica STL
Weck Laboratories, Inc. |
|
On-Call Acoustical Ceiling Services (B073275029)
(3 Bids Received) |
Mike Trapp |
06-22-2007 |
E.G Acoustics
B.R. Acoustics
Tasko Diversified |
$69.00 per hr.
$74.95 per hr.
$89.64 per hr.
See Bid Eval |
On-Call Door Hardware & Lock Services (B073275028)
(3 Bids Received) |
David Berry |
06-22-2007 |
C.M. Long General Cont., Inc.
Capitol Builders Hardwar, Inc.
Rex Lock & Safe (Bode & Bode) |
$75.70 per hr.
$83.00 per hr.
$85.00 per hr.
See Bid Eval |
On-Call Electrical - General (+ 600 Volts) Services (B073275031)
(1 Bid Received) |
Rudy Bargas |
06-22-2007 |
Harreld's High Voltage |
$611.88 per hr.
See Bid Eval |
On-Call Electrical - General (- 600 Volts) Services (B073275030)
(4 Bids Received) |
Rudy Bargas |
06-22-2007 |
Benbow Electrical Co.
Jackson Electric
Elite Power
Leo Electric |
$62.50 per hr.
$85.00 per hr.
$88.00 per hr.
$95.00 per hr.
See Bid Eval |
Jacinto Creek Park - Phase 2 (LU38) (B074727021)
(7 Bids Received) |
Dennis Day |
06-20-2007 |
JM Slover Inc.
Olympic Land Construction
Ad Land Venture
Gold Valley Construction
Hemington Landscape |
$603,309.40
$607,393.35
$622,646.96
$630,714.10
$663,805.41 |
Water Meter Retrofit - Phase 2 (ZS08) (B073331040)
(8 Bids Received) |
Chris Powell |
06-20-2007 |
Florez Paving
Navajo Pipelines
Peterson General
Arrow Construction
General Engineering Inc. |
$792,323.00
$814,400.00
$884,425.00
$907,525.00
$931,337.00 |
Gardenland Park (LC12)
(B074727019)
(6 Bids Received) |
Jeff Nittka |
06-20-2007 |
Sierra Asphalt
Solo Landscaping
Martin Brothers Construction
Biondi Paving
Olympic Land Construction |
$34,160.00
$42,007.70
$43,162.31
$44,605.05
$50,638.59
See Bid Eval |
21st St/Freeport Blvd Two-Way Conversion (SL01) (B073431021)
(2 Bids Received) |
Nader Kamal |
06-20-2007 |
Pacific Excavation Inc.
Prism Engineering |
$1,129,508.00
$1,443,713.50 |
903 Del Paso Blvd Wall Project (B073431022)
(4 Bids Received) |
Ofelia Avalos |
06-19-2007 |
K & L General Engineering
Nor Cal Masonry Builders
John D. Wait Masonary
RA Nemetz Construction |
$33,379.00
$45,846.00
$58,100.00
$96,900.00 |
RFQ for Financial and Special Tax Consultant (P074915001)
(1 Proposal Received) |
Sini Makasini |
06-14-2007 |
Did Not Qualify |
|
3 Axle Dump Truck (B071181091)
(4 Bids Received) |
Bill Tierce |
06-13-2007 |
Bonander Truck
Riverview Int'l Trucks, Inc.
Sacramento Truck Center
Western Truck Center |
$840,063.44
$840,597.41
$855,312.14
$881,514.79 |
Fremont Park Improvements Rebid (B074727020)
(4 Bids Received) |
Julia Cox |
06-13-2007 |
Rams Construction
Olympic Land Construction
Tricon
Aquatic Environments, Inc. |
$88,999.76
$130,000.40
$138,080.00
$155,750.00 |
Garcia Bend Park Tennis Court & Picnic Shelter (B074727018)
(6 Bids Received) |
Julia Cox |
06-13-2007 |
Biundo Landscape Construction
Olympic Land Construction
SLS Constructors, Inc.
Biondi Paving
C&C Construction |
$280,632.00
$294,550.97
$304,000.00
$329,017.64
$335,391.00 |
Recreation Publications (B071181093)
(6 Bids Received) |
Linda Taylor |
06-08-2007 |
Wesco Graphics
Commerce Printing
W.W. Hobbs Printing
Graphic Focus
Trudesign Graphics
|
$20,654.42
$24,247.00
$26,197.00
$26,548.96
$30,155.50
See Bid Eval
. |
Traffic Signal and Streetlight Poles (B073498007)
(4 Bids Received) |
Steve Krecek |
06-08-2007 |
Wesco Distribution
GEXPRO/GE Supply
Hi-Line Electric
Graybar Electric |
$61,146.00
$87,277.91
$90,092.42
$99,759.38
See Bid Eval |
Consultant Services for the Stone-Boswell Project Environmental Impact Report Preparation (P074881005)
(... Proposals Received) |
Shelly Amrhein |
06-06-2007 |
Not Yet Available |
|
Franklin Blvd/Fruitridge Rd Intersection Improvements (B073431020)
(5 Bids Received) |
FaramarzAnsari |
06-06-2007 |
C&C Construction Inc.
Biondi Paving
Granite Construction Co.
Vanguard Construction
Martin Brothers Construction |
$429,751.00
$493,617.40
$499,999.00
$503,064.00
$547,097.70
|
Northgate Park Shade Structure (B074727017)
(2 Bids Received) |
Roy Tatman |
06-06-2007 |
Shade Comfort Inc.
SLS Constructors |
$65,979.98
$84,000.00 |
Recycled Cut Paper (B071181090)
(... Bids Received) |
Sonny Eboigbe |
06-05-2007 |
Canceled |
|
Aluminum Sheeting (B071181092)
(8 Bids Received) |
Christine Slay |
06-04-2007 |
US Standard Signs
Quality Metals, Inc
Charlston Aluminum
Safeway Sign Co.
Gerlinger Steel
|
$36,381.79
$36,430.28
$40,406.25
$40,729.50
$41,974.01
See Bid Eval |
Virgin Cut Paper (B071181089)
(... Bids Received) |
Karen Wright |
06-04-2007 |
Canceled |
|
RFQ for On-Call Consultants for Landscape Architecture Services (Q074747001)
(9 Qualifications Received) |
Steven Giguere |
06-04-2009 |
Callender Assoc.
Stantec
The HLA Group
RHAA |
See Eval |
Install Vehicle Identification Boxes (B073259013)
(0 Bids Received) |
Matt Winkler |
06-01-2007 |
No Bid's |
|
K Street Streetscape RFP (ED11)
(3 Proposals Received) |
Melissa Anguaino |
05-31-2007 |
Amphion Environ. Inc.
WRG Design Inc.
Walker Macy |
|
Haggin Oaks & Bing Maloney Golf Course Cart Wash Pads (OB61)
(3 Bids Received) |
Sue Akiyama |
05-30-2007 |
Combs Construction
C&C Construction, Inc.
BRCO Constructors, Inc. |
$151,931.00
$189,129.00
$209,000.00 |
Curtis Park Tennis & Basketball Court Renovations (LY01) (B074727015)
(1 Bid Received) |
Tim Hopper |
05-30-2007 |
Biondi Paving |
$72,300.00 |
Roadway Striper (B071181088)
(3 Bids Received) |
Marc Robles |
05-30-2007 |
Western Truck Parts
Riverview Int'l Trucks
Endisys LLC |
$209,261.00
$210,473.05
$225,736.25 |
Request for Proposal for Parking Citation Hearing Officer Services (P071181082)
(1 Proposal Received) |
Walker Black |
05-29-2007 |
McGeorge School of Law |
$35.00 per Hr |
Laboratory Services for Groundwater Analysis (P07336152)
(1 Proposal Received) |
Marty Strauss |
05-29-2007 |
Cal Science |
|
300 Richards-River District City Service Center RFQ
(Q073282035)
(5 Qualifications Received) |
Bonnie Slavin |
05-25-2007 |
John F. Otto, Inc.
Q&D Construction
Roebbelen
Rudolph and Sletten
Unger Construction |
|
2007 City Street Overlay Project (RM71) (B073431019)
(5 Bids Received) |
Ricky Chuck |
05-23-2007 |
AC General Engineering
Martin Brothers Construction
Granite Construction
Martin General Engineering
Vintage Paving Co. |
$673,924.00
$687,098.00
$749,754.00
$770,696.00
$953,489.00
See Bid Eval |
City Landfill General Engineering Technical Support Svs. (Q07336149)
(2 Qualifications Received) |
Marty Strauss |
05-21-2007 |
SCS Engineers
Shaw Environmental |
|
Memorial Auditorium Foundation Waterproofing
(B073282027)
(2 Bids Received) |
YadiKavakebi |
05-16-2007 |
Ashron Construction
Best Inc. |
$1,294,275.00
$1,940,300.00 |
Fairfield/Cantalier Alley Sewer Replacement - Calvados Ave. to Arden Way (XI56) (B073331039)
(4 Bids Received) |
Dale Mathison |
05-16-2007 |
Navajo Pipelines Inc.
Florez Paving
AC General Engineering
North Star Construction |
$83,200.95
$90,800.00
$94,795.00
$199,050.00
See Bid Eval |
Request for Proposal for Actuarial Services (P071546002)
(6 Proposals Received) |
Patrick Flaherty |
05-14-2007 |
Richard E. Sherman & Associates
Robert Hughes Associates
Oliver Wyman Actuarial
Deloitte Consulting LLP
AMI Risk Consultants, Inc.
Bickmore Risk Services |
|
Mitigated Negative Declaration Preparation (P084885001)
(4 Proposals Received) |
Dana Allen |
05-11-2007 |
Environmental Stewardship and Planning, Inc.
Jones and Stokes
RBF Consulting
CDM |
|
Transformer Oil Reconditioning (P073381001)
(2 Proposals Received) |
Ron Adams |
05-10-2007 |
Siemens
Eaton Cutler Hammer |
$18,093.00
$36,595.00 |
Public Opinion Research Project (P070310003)
(13 Proposals Received) |
Michelle Heppner |
05-10-2007 |
ETC Institute
National Research Center
Migliore Consulting
Leadership Factor, Inc
J D Franz |
$50,900
$55,149
$76,799
$76,900
$81,126. |
Picnic Area Improvements at Belle Coolidge, Lawrence & Woodbine Parks (LR92, LY21, LY31) (B074727013)
(8 Bids Received) |
Sue Akiyama |
05-09-2007 |
Solo Landscaping
JM Slover Inc.
SLS Constructors Inc.
TLB Builders
K & L General Engineering |
$241,706.50
$251,479.00
$261,000.00
$261,333.78
$263,100.00
See Bid Eval |
Del Paso Regional Park Wetland Project (WM66)
(B073331038)
(6 Bids Received) |
Mark Elliot |
05-09-2007 |
North Star Construction
Restoration Resources
Diamond D General Engineering
Ad Land Venture
Martin Bros. Construction |
$526,900.00
$540,735.80
$661,251.00
$875,718.18
$886,200.00
See Bid Eval |
North Laguna Wildlife Bike Trail (HC46) (B074727014)
(8 Bids Received) |
Jeff Nittka |
05-09-2007 |
Martin General Engineering
Biondi Paving
Macouley Construction
American Landscape & Concrete
Gateway Landscape Const. Inc |
$201,631.00
$221,725.00
$226,294.00
$226,970.00
$241,851.00 |
Crystalline Sodium Fluoride
(B071181084)
(2 Bids Received) |
Christine Slay |
05-09-2007 |
Brenntag
American International Chemical |
$73,750.00
$80,000.00 |
Refuse Trucks (B071181083)
(2 Bids Received) |
Marc Robles |
05-09-2007 |
Sacramento Truck Center
Western Truck Parts |
$1,076,233.65
$1,302,899.00 |
On-Call Trenchless Services (B073275026)
(0 Bids Received) |
Gary Holm |
05-07-2007 |
No Bids |
|
On-Call Roofing Services (B073275025)
(2 Bids Received) |
Mike Trapp |
05-07-2007 |
Hester Roofing
Madsen Roofing |
$75 per hr
$87 per hr |
On-Call Fire Detection System Services (B073275024)
(1 Bid Received) |
Gary Holm |
05-07-2007 |
Sentinel Fire |
$105 per hr |
On-Call Fencing Services - Chain Link & Wrought Iron
(B073275023)
(1 Bid Received) |
Kevin Ohare |
05-07-2007 |
Dynaram Construction |
$145 per hr |
Police & Fire Enterprise Protection Storage (B072158015)
(2 Bids Received) |
Sharon Watson |
05-04-2007 |
Allied Network Solutions
CDW-G |
$65,000.00
$139,998.00
See Bid Eval |
Deep Tine Aerator (B074280002)
(1 Bid Received) |
Mike Kerton |
05-03-2007 |
H.V. Carter Co., Inc |
$25,522.74 |
Fruitridge & Bradford/Wilkinson Traffic Signal (SM15) (B073431018)
(4 Bids Received) |
Kaleb Haile |
05-02-2007 |
Pacific Excavation Inc.
RAH
M&M Electric
Tennyson Electric, Inc. |
$203,620.00
$215,666.00
$221,023.00
$277,415.00 |
Witter Ranch Park - Phase 2 (LU93) (B074727012)
(3 Bids Received) |
Sue Akiyama |
05-02-2007 |
JM Slover Inc
Olympic Land Construction
BRCO Constructors, Inc. |
$341,496.00
$357,199.65
$426,000.00
See Bid Eval |
Armored Car Services (B071181037)
(2 Bids Received) |
Marc Robles |
05-02-2007 |
Silva AT Systems
Loomis |
$65,169.11
$176,037.40 |
Enterprise Job Scheduler System (P071345001)
(5 Proposals Received) |
Thanh Vo |
05-02-2007 |
IBM
BMC
Computer Associates
UC4 Software
Tidal Software |
|
Construction Management Services for West El Camino Ave Bridge Replacement (P073431009)
(9 Proposals Received) |
Ricky Chuck |
05-01-2007 |
Salaber
Nolte
Vali Cooper
CMTS
Balckburn
TRC
URS
Harris
TRS |
|
South Roadside Weed Abatement (B073497003)
(7 Bids Received) |
Stephanie Fraser |
04-30-2007 |
Valley Landscape
Clark Pest
Pegasus Pest
Tru-Green Chemlawn
Pestmaster Services |
$13,385.00
$13,885.39
$17,117.00
$17,852.69
$24,316.00
See Bid Eval |
North Roadside Weed Abatement (B073497004)
(7 Bids Received) |
Stephanie Fraser |
04-30-2007 |
Valley Landscape
Clark Pest
Pegasus Pest
Tru-Green Chemlawn
Pestmaster Services |
$35,100.00
$36,562.00
$43,538.00
$46,791.63
$64,027.00
See Bid Eval |
Miscellaneous Small Power Equipment (B074728009)
(3 Bids Recieved) |
Wally Cole |
04-30-2007 |
United Rentals, Inc.
Acme Saw & Supply
Bliss Power Lawn Equip. |
$82,351.18
$80,669.90
$80,924.00
See Bid Eval |
IItronic GoBook XR-1 Laptops (B071181086)
(3 Bids Received) |
Capt. Scott Williams |
04-30-2007 |
Raymar
New Tech Solutions
Cyber Computers |
$90,639.08
$91,810.32
$94,676.48
See Bid Eval |
Green Rubbermaid 55-Gallon Round Brute Cans (B074728008)
(7 Bids Received) |
Wally Cole |
04-30-2007 |
Dixon Hardware & Lumber Co.
Recy-Cal Supply Company
S and S Supplies & Solutions
United Rentals, Inc.
Sac Val Janitorial |
$18,244.23
$18,339.05
$19,912.20
$23,105.91
$23,881.71
See Bid Eval |
Sacramento River Water Treatment Plant (SRWTP) (B073331036)
(4 Bids Received) |
Craig Chalmers |
04-27-2007 |
Dillard
Empire Trucking
Chavez
Manley |
$94,145
$94,224
$94,250
$94,250 |
2007 Seal Coat Project (B073431015)
(3 Bids Received) |
Greg Smith |
04-25-2007 |
Valley Slurry Seal Co.
Intermountain
Calif. Pavement Maint. |
$2,859,166.71
$2,999,264.47
$3,189,210.81 |
Permanent and Semi-Permanent Fencing Services (B074881003)
(1 Bid Received) |
Thomas Adams |
04-25-2007 |
Dynaram Construction |
Various |
Washington Park Infill Street Lighting (SU21) (B073431019)
(3 Bids Received) |
Sompol Chatusripitak |
04-24-2007 |
Dynaram Construction
Richard A. Heaps Elec.
Pacific Excabation |
$17,466.00
$21,846.00
$25,731.00 |
07 Irrigation Parts (B074728007)
(2 Bids Received) |
Wally Cole |
04-23-2007 |
Sprinkler Service & Supply
Water Rite Products |
$73,324.00
$83,054.00
See Bid Eval |
RFP: Short Circuit Coordination Studies and Arc-Flash Hazard Analysis (P073383001)
(6 Proposals Received) |
Ron Adams |
04-23-2007 |
Eaton/Indust. Electical Co.
SRP
Stantec
DCCK
CDM |
$13,000.00
$14,100.00
$16,500.00
$39,460.00
$62,184.00 |
Concierge Services for City Owned Facilities RFQ (Q073431001)
(2 Qualifications Received) |
Beverly L Garland |
04-25-2007 |
Concierge Services
City Concierge |
|
Community Convention
(P074912004)
(2 Proposals Received) |
Susanne Cook |
04-23-2007 |
Jones & Stokes
Valley Vision |
|
Request for Qualifications for Plan Review, Inspection and/or Permit Counter Services (Q074811004)
(... Qualifications Received) |
Ed Short |
04-20-2007 |
Not Yet Available |
|
Wisconsin, Indiana & Bowman Avenues Water Main Replacement Project (ZS02)
(B073331035)
(8 Bids Received) |
Stu Williams |
04-18-2007 |
Navajo Pipelines
L.R Gomez Constuction
Civil Engineering Const.
Newland Entities
West Valley Const. |
$379,653.00
$403,800.00
$435,100.00
$438,632.00
$439,550.00
See Bid Eval |
CWTP Motor Control Center (MCC) "F" Replacement Project (XN36) (B073331037)
(1 Bid Received) |
Jian Zhuang |
04-18-2007 |
Interstate Const., Inc. |
$635,577.00 |
Bottles of Mace (B072124014)
(... Bids Received) |
Milt Payne |
04-18-2007 |
All Bids Rejected |
|
Automotive and Industrial Bearings, Seals, Automotive Seals (B071181045)
(5 Bids Received) |
Louane Roina |
04-18-2007 |
Fleetpride
Napa Auto Parts-Genuine Parts Ctr
Factory Motor Parts
Motion Industries
Industrial Electrical Company |
$7,635.90
$8,612.15
$8,716.04
$9,245.09
$9,824.50 |
Water Tank Truck (B073259012)
(2 Bids Received) |
Bill Tierce |
04-16-2007 |
Holt of California
Hertz |
$81,749.00
$85,000.00
See Bid Eval |
65th Expressway Roadsides (B073497001)
(4 Bids Received) |
Stephanie Fraser |
04-16-2007 |
Dominguez Landscape
Moodey Incorp
Valley Landscape
Cazares Landscape |
$8,406.00
$8,900.00
$10,500.00
$13,000.00
See Bid Eval |
300 Richards Blvd (B073497002)
(7 Bids Received) |
Stephanie Fraser |
04-16-2007 |
Plantech Landscape
Moodey Inc.
Empire Landscape
Oliver Landscape
Domingues Landscape |
$8,700.00
$9,900.00
$13,760.00
$13,800.00
$14,196.00
See Bid Eval |
Old Sacramento Solid Waste Collection and Diversion Program RFP (P074360001)
(2 Proposals Received) |
Annabeth Stem |
04-13-2007 |
Atlas Disposal Industries
City of Sac, Solid Waste |
|
City College Light Rail Station (P073431008)
(5 Proposals Received) |
Ryan Moore |
04-13-2007 |
David Evans & Assoc
TRC
Nolte
URS
Lim & Nascimento |
|
North Natomas Regional Park (LX66) (B074727011)
(4 Bids Received) |
StevenGiguere |
04-11-2007 |
C&C Construction , Inc.
Gold Valley Const.
Hemington Landscape
Olympic Land Const. |
$811,249.00
$817,041.50
$1,131,783.00
$1,333,946.00
See Bid Eval |
| Colonial Heights Street Improvements (RR22) (B073731015)
(10 Bids Received) |
FaramarzAnsari |
04-11-2007 |
Central Valley Eng. &
Martin General Eng.
Western Engineering
Biondi Paving
Vintage Paving, Co. |
$171,532.75
$177,314,00
$178,771.00
$186,511.00
$196,333.11 |
Radio Equipment Services (B071181080)
(2 Bids Received) |
Nicole Bilich |
04-11-2007 |
Motorola Inc.
Telepath Commercial Comm |
$368,833.00
$402,006.84 |
Enterprise Job Scheduler System (P071345001)
(5 Proposals Received) |
Thanh Vo |
04-11-2007 |
IBM
BMC
Computer Assoc.
UC4 Software
Tidal Software, Inc. |
|
ESRI ArcGis Standard Runtime Windows License (B073351049)
(1 Bid Received) |
Ron Fujioka |
04-06-2007 |
ESRI |
|
24th St & Hogan Dr Traffic Installation (B073431014)
(2 Bids Received) |
John Matoba |
04-04-2007 |
Pacific Excavation, Inc.
R.A.H. Elect. Contractors, Inc. |
$209,302.00
$277,781.00 |
Peregrine Park (LX46) (B074727010)
(6 Bids Received) |
JeffNittka |
04-04-2007 |
Olympic Land Const
Hemington Landscape
JM Slover Inc.
Goodland Landscape Const.
AdLand Venture
|
$1,206,532.00
$1,218,977.00
$1,355,847.69
$1,379,970.00
$1,437,046.30
See Bid Eval |
Regency Park Phase 2 (LV78) (B074727009)
(6 Bids Received) |
TinWahWong |
04-04-2007 |
Olympic Land Const.
Goodland Landscape Const.
AdLand Venture
Park West Landscape
JM Slover Inc. |
$1,065,155.82
$1,176,007.95
$1,190,148.39
$1,255,164.00
$1,344,584.81 |
Utility Bid Trucks (B071181078)
(3 Bids Received) |
Marc Robles |
04-04-2007 |
Riverview Int'l Trucks, Inc.
Sacramento Truck Center
Bonander Truck |
$884,660.13
$898,617.72
$1,061,306.70 |
State Transportation Legislative Advocacy Services (P073431007)
(0 Proposals Received) |
Azadah Doherty |
04-02-2007 |
None Received |
|
On-Call Fire Sprinkler Services (B073275017)
(2 Bids Received) |
LouieMaldonado |
03-30-2007 |
Nor-Cal Fire Protection
Marquee Fire Protection |
$65 per hr
$105 per hr |
On-Call Flooring Services (B073275019)
(3 Bids Received) |
Mike Trapp |
03-30-2007 |
Dynamic Commercial
A&P Flooring
Waldo Bowers Floor |
$62 per hr
$75 per hr
$85 per hr |
On-Call HVAC - Large Tonnage (Over 21 Tons) Commercial Services (B073275020)
(3 Bids Received) |
NghiemNguyen |
03-30-2007 |
American Chiller
Indoor Environmental
Thermal Air |
$91.70 per hr
$95 per hr
$128.92 per hr |
On-Call HVAC - Small Tonnage (20 Tons & Under) Light Commercial Services (B073275021)
(3 Bids Received) |
NghiemNguyen |
03-30-2007 |
On Line Heating & Air
Mielcasz & Associates
Yamas Controls Grp |
$65 per hr
$70 per hr
$105 per hr |
School Radio System for Kennedy High School (B071181081)
(1 Bids Received) |
Chris Slay |
03-29-2007 |
ComTech Communications |
$98,572.90 |
Fulton Ave Development Project (CB37) (B073431013)
(16 Bids Received) |
Jon Blank |
03-28-2007 |
Teichert Construction
McGuire & Hester
Sierra National Construction
Sierra Nevada Construction
Envirocon |
$3,455,048.00
$3,547,000.00
$3,597,175.00
$3,793,007.00
$3,988,587.50 |
Water Distribution Utility Vans (B071181077)
(6 Bids Received) |
Mark Robles |
03-28-2007 |
Western Truck Fab
American Truck & Trailer Body
Riverview Int'l Trucks
Sacramento Truck Center
Bonander Trucks |
$150,203.50
$177,356.50
$294,107.38
$297,831.23
$310,505.00
|
Reproduction and Plan Room Services (Re-Bid) (B071181073)
(3 Bids Received) |
Rachel Rosas |
03-28-2007 |
Signature Reprographic
Zuprinco Printing
Century Graphics |
$1,317.05
$1,371.42
$2,611.03 |
Police Ammunition (B072124013)
(2 Bids Received) |
Milt Payne |
03-27-2007 |
Adamson Police Products
Western Law Enforcement |
$49,020.00
$51,471.00
See Bid Eval |
Unicenter Licenses and 3 year maintenance (B071311010)
(3 Bids Received) |
Jim Berg |
03-16-2007 |
Cyber Computers
Allied Network Solutions
Insight |
$50,025.00
$73,950.00
$138,127.00
See Bid Eval |
Recycling Cans (B074728005)
(2 Bids Received) |
Wally Cole |
06-16-2007 |
Recy-Cal Supply
Preeminence |
$18,150.49
$23,985.00
See Bid Eval |
Recycle Can Lids With Loop Cable Attachment (B074728006)
(1 Bid Received) |
Wally Cole |
03-16-2007 |
Recy-Cal Supply |
$65,710.26
See Bid Eval |
Mobile Vu 12.1 LCD Display w/Touch Screen and safety glass (B072541009)
(2 Bids Received) |
Scott Williams |
03-16-2007 |
L3 Communications
Cyber Computers Inc. |
$39,288.00
$40,800.00
See Bid Eval |
Laptops and docking cradle for the Mobile Digital Computer project (B072541008)
(5 Bids Received) |
Scott Williams |
03-16-2007 |
New Tech Solutions Inc.
Trius Technologies
Raymar Info Tech Inc.
Cyber Computers Inc.
CDW-Government Inc. |
$24,950.00
$27,590.00
$28,077.80
$28,500.00
$28,700.00
See Bid Eval |
Gas Chromatograph and a Mass Spectrometer (B073351048)
(1 Bid Received) |
Roland Pang |
03-15-2007 |
Varian Inc. |
$44,205.00
See Bid Eval |
School Radio System for Albert Einstein High School (B071181079)
(1 Bid Received) |
Chris Slay |
03-15-2007 |
ComTech Communications |
$41,725.14 |
South Land Park Water Main Replacement - Phase 2 (ZL26) (B073331033)
(8 Bids Received) |
Brett Ewart |
03-14-2007 |
Florez Paving
Civil Engineering Construction
Navajo Pipelines
Preston Pipelines
West Valley Construction |
$1,293,560.00
$1,431,000.00
$1,434,394.00
$1,610,250.00
$1,619,719.00
See Bid Eval |
Water Meter Retrofit - Phase 1 (ZS08) (B073331034)
(6 Bids Received) |
Chris Powell |
03-14-2007 |
Newland Entities
Florez Paving
Navajo Pipelines
Vulcan Const & Maint.
Arrow Construction |
$483,442.00
$596,550.00
$612,830.00
$649,930.00
$655,420.00 |
Graffiti Abatement Services (B071181074)
(1 Bid Received) |
Noel Eusebio |
03-14-2007 |
Brooks Painting Inc. |
$21,525.00 |
| Fiscal Impact Forecasting & Utility User's Tax Revenue Estimating Tool (P071140001)
(3 Bids Received) |
Scott Pettingell |
03-12-2007 |
Muni Services |
$150,000.00 |
Various Traffic Signal Standards (B073498006)
(3 Bids Received) |
Steve Krecek |
03-09-2007 |
Hi Line Electric
Wesco Distribution
GE Supply |
$5,956.56
$6,530.00
$7,168.38
See Bid Eval |
40-foot Telescopic/Articulating Aerial Truck (B073259010)
(2 Bids Received) |
Jonathon Yee |
03-09-2007 |
Terex Utilities
U-Save Equipment Rentals |
$82,420.93
$91441.76
See Bid Eval |
2007/2008 Tow Services Agreement (P071187001)
(36 Proposals Received) |
Jason Contreras |
03-09-2007 |
30 Successful bidders |
Tow $160/ Hr
Storage $45/ day |
Removal of Solids and Cleaning of Vehicle and Refuse Truck Clean-Out Facilities (B073361046)
(7 Bids Received) |
Elizabeth Hall |
03-06-2007 |
Jack Kellum
O & T Investment
APS Environmental, Inc.
Safety-Kleen Systems, Inc.
Palisades Recovery Services |
$35,000.00
$40,000.00
$54,036.00
$55,490.00
$62,760.00 |
| Rehabilitation of Sewer Manholes - 2007 (XI71) (B073331032)
(5 Bids Received) |
Sonia Lopez |
03-02-2007 |
Arrow Construction
AC General Engineering
Florea Paving
Navajo Pipelines, Inc.
K & L General Engineering |
$91,890.00
$93,911.50
$98,800.00
$125,300.00
$138,970.00
See Bid Eval |
Temporary Fencing Services (B071181076) (B071181076)
(... Bids Received) |
Randy Stratton |
03-01-2007 |
No Bids Recieved |
|
School Radio System for McClatchy High School (B071181072)
(1 Bid Received) |
Chris Slay |
03-01-2007 |
Comtech Communications |
$47,943.30 |
Permanent and Semi Permanent Fencing Services 9B071181075)
(... Bids Received) |
Ron O'Connor |
03-01-2007 |
No Bids Recieved |
|
School Radio System for Rosement High
(B071181062)
(1 Bid Received) |
Chris Slay |
03-01-2007 |
ComTech Communications |
$94,092.42 |
Stockton Blvd Water Transmission Main Replacement - R Street to 2nd Ave (B073331031)
(8 Bids Received) |
Michelle Carrey |
02-28-2007 |
T & S Construction
Preston Pipelines
West Valley Construction
AC General Engineering
McGuire & Hester |
$2,093,625.00
$2,140,312.00
$2,277,115.00
$2,419,936.00
$2,527,150.00 |
| Central Library Elevator Renewal (B073275018)
(1 Bid Received) |
Tony Alexander |
02-28-2007 |
Elevator Technology |
$209,800.00 |
City of Sacramento Housing Element Update & Implementation Assistance (P074912003)
(3 Proposals Received) |
Desmond Parrington |
02-23-2007 |
Pacific Municipal Consultants
Economic and Planning Systems
EDAW |
$97,305.00
$180,000.00
$199,660.00 |
Sump 26 Electrical Improvements (WN11) (B073331030)
(1 Bid Received) |
Paul Barnes |
02-21-2007 |
Interstate Const. Inc. |
$348,038.76 |
U/V Alley Sewer Replacement - 8th to 9th Street (XN52) (B073331029)
(7 Bids Received) |
RosaUlloa |
02-21-2007 |
Florez Paving
Navajo Pipelines
AC General Engineering
Preston Pipelines
North Star Const. |
$87,265.40
$92,947.00
$108,586.33
$124,014.00
$124,780.00
See Bid Eval |
Trucks, Vans & Sports Utility Vehicles (B071181065)
(7 Bids Received) |
Chris Slay |
02-21-2007 |
Swift Jeep, Chrysler
Hoblit Fleet Group
Burch Ford
Harrold Ford
Downtown Ford |
$2,519,347.81
$2,535,538.71
$2,683,878.45
$2,721,359.17
$2,785,574.21 |
Swimming Pool Chemicals (B071181046)
(4 Bids Received) |
Louane Roina |
02-21-2007 |
Sierra Chemical Co
Leslies Swimming Pool
Lincoln Equipment
Chem Quip |
$37,626.30
$70,053.59
$263,797.78
$286,870.91
See Bid Eval |
Nitrile Gloves (B071181059)
(4 Bids Received) |
Chris Slay |
02-21-2007 |
Coleman Medical
Comtrex Communications Ltd
NDJ Enterprises
Tronex Company
IMG |
$23,888.00
$24,180.00
$24,825.60
$25,052.00
$25,704.84 |
3 Axle Dump Truck
(B071181069)
(5 Bids Received) |
Chris Slay |
02-21-2007 |
Riverview Int'l Trucks
Bonander Truck Sales
Tec of California
Sacramento Truck Center
Western Truck Center |
$834,177.67
$834,329.39
$861,505.60
$873,888.24
$888,938.77 |
IIdentify and Access Management System Software and Implementation Services (B071313009)
(6 Bids Received) |
Patty McGeary |
02-20-2007 |
CA
IBM
M-Tech
Novell
Oracle Sun |
|
On-Call Fire System Services (B073275016)
(1 Bid Received) |
Louie Maldonado |
02-16-2007 |
Bid Rejected |
|
Redding Ave Bike & Pedestrian Improvements (P073431006)
(... Proposals Received) |
John Scott |
02-16-2007 |
Not Yet Available |
|
FY08 Operating Budget, Capital Improvement Program, and Blueprint for Strategic Planning Document Pr (P071140002)
(2 Proposals Received) |
Virginia Smith |
02-16-2007 |
FedEx Kinko's
Uptown Graphics |
Rating 85
Rating 81 |
Solid Waste Services 20-Year Master Plan (Q07336148)
(3 Quotes Received) |
Marty Strauss |
02-12-2007 |
SCS Engineering
R3 Consulting
HDR and Shaw |
|
South Non-landscaped Medians (B071187071)
(5 Bids Received) |
Stephanie Fraser |
02-12-2007 |
Delta Landscape
Roush Landscape
Trugreen Chemlawn
Cazares Landscape
Dominguez Landscape
|
$30,854.33
$32,000.00
$33,808.00
$49,000.00
$64,144.00 |
North Non-landscaped Medians (B071187070)
(5 Bids Received) |
Stephanie Fraser |
02-12-2007 |
Roush Landscape
Delta Landscape
Trugreen Chemlawn
Cazares Landscape
Dominguez Landscape |
$32,000.00
$32,553.46
$36,324.00
$40,000.00
$67,680.00 |
Large Format Copier/Scanner
(B073431012)
(3 Bids Received) |
Bruce Cameron |
02-08-2007 |
California Surveying and Drafting Supply
Inland Business Systems |
|
Police Uniform Accessories
(B072124011)
(5 Bids Received) |
Milt Payne |
02-07-2007 |
Quartermaster, Inc.
Command Uniforms, Inc.
Sacramento Uniforms
Adamson Police Products
Rogue Tactical |
$11,689.25
$12,296.75
$12,975.00
$13,845.25
$17,755.00
See Bid Eval |
Janitorial and Building Maintenance Services (B071187023)
(19 Bids Received) |
Cynthia Kranc |
02-07-2007 |
Juan C. Rosello
Jerry's Carpet Care
Pacific Maintenance
SBM Site Services
Care Free Building Svcs |
$695,748.00
$710,337.40
$857,834.00
$966,129.21
$1,066,676.00
See Bid Eval |
D/E & E/F Alley Sewer Replacement - 25th to 27th Street (B073331028)
(6 Bids Received) |
Sonia Lopez |
02-07-2007 |
Florez Paving
Navajo Pipelines
Preston Pipelines
AC General
Sierra National Construction |
$496,805.00
$555,555,55
$633,287.00
$654,270.00
$719,940.00 |
John Deere Tractors (B071181063)
(2 Bids Received) |
Chris Slay |
02-07-2007 |
Valley Truck & Tractor
MME |
$193,362.55
$572,755.89 |
2007 Field Renovation Sand (B074728004)
(3 Bids Received) |
Randy Will |
02-06-2007 |
Beebe Industries, Inc.
Silica Resources, Inc.
West Coast Sand and Gravel |
$57,700.13
$62,275.91
$67,882.50
See Bid Eval |
2007 Field Renovation Material (B074728003)
(1 Bid Received) |
Randy Will |
02-06-2007 |
Sierra Pacific Turf Supply |
$24,820.00
See Bid Eval |
Saint Gobain Plastics chemical protective garments
(B072177012)
(1 Bid Received) |
Chris Hadley |
02-05-2007 |
Mallory Fire |
$55,959.00
See Bid Eval |
On-Call Fencing Services (B073275014)
(4 Bids Received) |
Cristine Chan |
02-02-2007 |
Bids Rejected |
|
Utility Bill Printing, Inserting, and Mailing Services (B071187061)
(0 Bids Received) |
Rachel Rosas |
02-01-2007 |
Canceled - to be Re-bid |
|
Process Service Services
(B071187067)
(... Bids Received) |
Rachel Rosas |
02-01-2007 |
Canceled-Bids rejected |
|
Soft Copper Pipe (B071181066
(7 Bids Received) |
Christine Slay |
01-31-2007 |
Argo Summit
Heick Supply
Buttes Pipe & Supply
Ferguson Ent
Sacramento Windustrial |
$89,732.40
$90,702.87
$92,172.56
$92,655.74
$95,607.65 |
Compact & Sport Utility Hybrid Vehicles (B071181064)
(7 Bids Received) |
Christine Slay |
01-31-2007 |
Senator Ford
Harrold Ford
Hoblit Group
Downtown Ford
Philpott Ford |
$381,795.46
$383,264.18
$391,010.54
$394,407.90
$400,201.60 |
Landscape Maintenance Services for the Sacramento River Water Treatment Plant and Intake (SRWTP) (B071187068)
(10 Bids Received) |
Barbara Collins |
01-30-2007 |
O & T Investment
California Landscape .
Roush Landscape
Cazares Landscaping
Valley Landscapes
Moody Incorporated |
$28,300.00
$30,418.00
$30,804.00
$32,250.00
$35,343.60
$36,240.00
See Bid Eval |
Employee Opinion Survey
(P070310002)
(10 Proposals Received) |
Mark Prestwich |
01-30-2007 |
Northwest Research Grp
O'Neil Associates
JD Franz Research, Inc.
DRI Consulting
Public Policy Associates
National Research Center
Fairbank, Maslin, Maullin
Kirchhoff & Associates
Migliore Consulting
Hay Group |
|
65th St. Station Area Study
(P073431005)
(2 Proposals Received) |
Tara Goddard |
01-26-2007 |
The HLA Group
Dowling and Assoc.
Environmental Stewardship and Planning
Economic & Planning Systems
Nichols Consulting Engineers |
|
Alder Park Rebid (LX56)
(B074727007)
(10 Bids Received) |
Jeff Nittka |
01-24-2007 |
Gold Valley Const
Hemington Landscape Svcs
Olympic Land Const
Parker Landscape Dev
Ad Land Venture |
$346,217.05
$348,779.00
$351,202.20
$364,317.00
$368,370.35
See Bid Eval |
University Park South
(B074727008)
(8 Bids Received) |
Steve Giguere |
01-24-2007 |
Ad Land Venture
Solo Landscaping
Olympic Land Const
JM Slover Inc
Parker Landscape Dev |
$100,292.16
$103,810.00
$112,027.50
$114,893.90
$119,074.00
See Bid Eval |
Engine Generator Modifications-Clean Cam-Rebid
(B073350047)
(1 Bid Received) |
Bill Miller |
01-23-2007 |
Clean Cam Technology |
$86,900.00
See Bid Eval |
George Sim Community Center Expansion
(Q073282015)
(1Qualification Received) |
Dave Morgan |
01-19-2007 |
Brown Construction |
|
CSI Expansion
(B07E268010)
(8 Bids Received) |
Barbara Anderson |
01-18-2007 |
17th St. Photo Supply Inc.
B&H Photo-Video
Imaging Products Int'l
Action Camera
Pardee's Cameras |
$27,385.00
$27,729.00
$28,755.00
$29,410.00
$29,582.20
See Bid Eval |
Title Report Search Services (B074651005)
(2 Bids Received) |
Rachel Rosas |
01-17-2007 |
Placer Title Company
SZS Consultanting Grp |
$44,650.00
$109,625.00 |
Wide Area Rotary Mowers (B071181057)
(1 Bid Received) |
Christine Slay |
01-17-2007 |
H V Carter Co Inc |
$196,956.18 |
Sump 128 Electrical Improvements (WM46) (B073331026)
(4 Bids Received) |
Paul Barnes |
01-17-2007 |
JR Sharp Construction
Interstate Construction
Johnson Mechanical
Westcon Construction |
$368,000.00
$382,025.00
$447,500.00
$461,310.00 |
Del Paso Rd/Main Avenue Transmission Main Potholing (B073331027)
(8 Bids Received) |
Warren
Peterson |
01-12-2007 |
Pacific Utility Construction
Bailey's Trenchless, Inc.
Exaro Technologies Corp.
Golden State Utility Co.
Frank Medina General |
$24,990.00
$27,405.00
$30,576.00
$32,199.72
$35,910.00
See Bid Eval |
Demolition of 802 K Street (B074653007)
(5 Bids Received) |
Josh Pino |
01-12-2007 |
Advantage Demo. & Eng.
GW Demo
MS Emerald Construction
Delta Oilfield Services, Inc.
P & P Wrecking Inc. |
$19,536.24
$25,000.00
$29,221.00
$29,827.00
$54,800.00
See Bid Eval
|
RFP St. Rose of Lima Park Landscape Architect (P094451009)
(8 Proposals Received) |
Melissa Anguiano |
01-12-2007 |
Quadriga Landscape Architects
WRG Design Inc
Wood Rodgers
RJM Design Group, Inc |
|
Street Name Sign Blanks (B073495002)
(3 Bids Received) |
Tom Webber |
01-11-2007 |
Zumar Industries Inc.
Safeway Sign Co.
ZAP Manufacturing Inc. |
$3695.75
$3,824.25
$4,575.00
See Bid Eval |
Performing Arts Facility Study (P074310001)
(9 Proposals Received) |
Linda DeLong |
01-11-2007 |
Economics Research Associate
|
|
Sacramento Marina South Basin Renovation (IA66) (B073331025)
(3 Bids Received) |
Richard Dalrymple |
01-10-2007 |
A.C.C. West Coast Inc.
Bellingham Marine
Sierra National Construction |
$8,913,711.00
$11,676,379.00
$11,787,890.00 |
Root Control Application - 2007 (XI76) (B073331022)
(4 Bids Received) |
Sonia Lopez |
01-10-2007 |
Empire Landscaping
Root Tamers
Dukes Sales & Service
Pacific Sewer Maintenance |
$136,547.00
$149,157.50
$161,699.50
$187,726.00 |
Chiller Renewal at Central Library (P073282009)
(3 Proposals Received) |
Keith Roberts |
01-10-2007 |
IES
American Chiller
American Chiller |
$158,730.00
$263,800.00
$283,684.00 |
Capitol Garage HVAC Replacement (B073282013)
(5 Bids Received) |
Arnold Sotelo |
01-03-2007 |
Purdy Builders, Inc.
Division 5-15
Hometown Construction
Bangar Contractors
Bobo Constuction |
$1,195,000.00
$1,480,000.00
$1,693,000.00
$1,720,000.00
$1,724,000.00
See Bid Eval |
Sump 37 Pump Station Electrical Improvements (B073331021)
(4 Bids Received) |
Jian Zhuang |
01-03-2007 |
Westcon Construction
JR Sharp Construction
Interstate Construction
Gwinn Construction |
$298,136.00
$299,500.00
$318,862.00
$389,566.00 |
Plumbing Supplies (B071181026)
(4 Bids Received) |
Christine Slay |
01-03-2007 |
National Meter
Water Rite Products
Ferguson Enterprises
Groeniger & Co. |
$106,465.92
$151,015.90
$793,184.31
$883,261.33 |
Copper Pipe (B071181058)
(... Bids Received) |
Christine Slay |
01-03-2007 |
Canceled |
|
Automatic Transmission Repair Services (B071187055)
(1 Bid Received) |
Rachel Rosas |
01-03-2007 |
House of AutomaticTransmissions |
$76,515.00
See Bid Eval |
Arden Way ITS Controllers (B073431012)
(1 Bid Received) |
Greg Smith |
01-02-2007 |
Econolite Control Products |